View a system budget
- Last UpdatedMay 07, 2026
- 1 minute read
View the budget of a cost account.
-
Navigate to the s10006 Project System Budget screen.
-
In the Current Project control block, from the Project dropdown, select the ID of the required project.
-
To refresh the screen, select the F5 key.
-
In the Levels and Systems grid, select a row.
-
On the s10006 menu, in the Show Budget Actions group, perform one of the following:
-
To view the full budget, select Full Budget.
-
To view the total budget, select Totals Budget.
-
To view the material budget, select Material Budget.
-
To view the sub-contract budget, select Sub-Con Budget.
-
To view the man-hour budget, select Hour Budget.
-
To view the direct expenses budget, select Expense Budget.
-
To view the man-hour budget in hours, select Hour Budget (Hour).
-
To view the cost detail budget in hours, select Cost Detail.
In the Systems grid, view the required budget.
-